Bottom-Up Estimating
Bottom-up estimating, also referred to as first principles estimating, is the process of individually calculating the cost of each activity required to complete the project and summing these together to get the total project costs. We are building an estimate from the “bottom-up” or through the first principles.
Bottom-up estimating involved extensively reviewing the project scope, understanding exactly how the project will be delivered and then individually estimating each individual activity cost. Therefore, bottom-up estimating is the most accurate form of estimating but also takes the most time, resources, and skill. It is used when a cost estimate with a high level of certainty is needed. For example, when a contractor is submitting a tender for a fixed-price contract and needs price certainty to manage risk.
To produce a bottom-up estimate, we need to follow the following process:
1. Understand the project scope and decompose it into a series of individual activities
The first step in a bottom-up estimate is to thoroughly review the project scope. This means going through the project scope statement, drawings and specifications in detail.
The purpose of this is to develop a work breakdown structure. A work breakdown structure, or WBS for short, is a hierarchical decomposition of the project scope into the individual activities we need to complete to complete the project.
For example, if our project is to build a new swimming pool, we can break this scope down into different activities like excavation, paving and plumbing.
2. Develop the delivery methodology
The next step is to develop the delivery methodology. For each activity in our work breakdown structure, we need to know how we are going to complete it. Effectively, this means saying are we going to sub-contract it out to another company, or are we going to self-perform the works using our own individual labour, plant and materials.
3. Individually calculate the cost of each activity
Based on this delivery methodology, we then need to price the activity. If we have chosen to sub-contract the works, then we will need to get quotes from potential sub-contractors. If we have chosen to self-perform the work, then we’ll need to individually calculate the labour, plant and material costs, determine the overall quantum of work by doing a quantity take-off and come up with a production rate.
We will need to do this for each and every direct and indirect cost.
4. Sum the individual components together to calculate the total project costs
Now we have individually calculated the cost of each activity, the final step is to sum these all together. This will give us the total project cost.